2 x 35MW Coal Power Plant (RSFFB-2)
new cooling tower
Petron Units 3&4 Project
LOCATION: Limay Bataan
PROJECT: 2 x 35MW Coal Power Plant (RSFFB-2)
DURATION: July—October 2013
Created Date
October 17, 2024Created By
AdminPETRON 2D Turn-Around Project
Cooling Tower
PETRON 2D Turn-Around Project
LOCATION: Limay Bataan
PROJECT: PETRON 2D Turn-Around Project
DURATION: January, February 2014
Created Date
October 17, 2024Created By
AdminANDA 82MW Coal Power Plant
New Cooling Tower
ANDA 82MW Coal Power Plant
LOCATION: TIPCO Park, Mabalacat Pampanga
PROJECT: PETRON 2D Turn-Around Project
DURATION: November 2014– January 2015
Created Date
October 17, 2024Created By
AdminPRII Cooling Tower Turn-Around Project
Cooling Tower Turn-Around Project
PRII Cooling Tower Turn-Around Project
LOCATION: Mariveles Bataan
PROJECT: PRII Cooling Tower Turn-Around Project
DURATION: November—December 2015
Created Date
October 17, 2024Created By
AdminMaibarara Geothermal Power Plant Phase II
Installation of New Counterflow Cooling Tower
Maibarara Geothermal Power Plant Phase II
LOCATION: Sto. Tomas, Batangas
PROJECT: Maibarara Geothermal Power Plant Phase II
DURATION: July – August 2017
Created Date
October 17, 2024Created By
AdminEnergy Development Corporation
Installation of New Counterflow Cooling Tower
Energy Development Corporation
LOCATION: Ormoc, Leyte
PROJECT: Mahanagdong B- Rehabilitation of 8th Cell Counterflow Cooling Tower
DURATION: July –September 2017
Created Date
October 17, 2024Created By
AdminAERO Digester Rehabilitation
AERO Digester Rehabilitation
LOCATION: Binictican, SBMA
Zambales
CLIENT: Subic Water and Sewerage Co. Inc.
DURATION: July — September 2018
Created Date
October 17, 2024Created By
AdminPLC Installation (Filtration Plant)
PLC Installation (Filtration Plant)
LOCATION: Binictican, SBMA Zambales
CLIENT: Subic Water and Sewerage Co. Inc
DURATION: January 2018
Created Date
October 17, 2024Created By
AdminUltrasonic Clamp-on Flowmeter Installation
Ultrasonic Clamp-on Flowmeter Installation
LOCATION: Binictican, SBMA Zambales
CLIENT: Subic Water and Sewerage Co. Inc
DURATION:September 2017
Created Date
October 17, 2024Created By
AdminVarious Installation of Motorized Actuated Valves
Various Installation of Motorized Actuated Valves
LOCATION: Binictican, SBMA Zambales
CLIENT: Subic Water and Sewerage Co. Inc
DURATION: April–May 2015