Supply of FRP Hot Water Basin and Splash Bars

Supply of FRP Hot Water Basin and Splash Bars

LOCATION: Tongonan Geothermal Plant
CLIENT: Energy Development Corp.
DURATION: September 2017

Various Installation of Motorized Actuated Valves

Various Installation of Motorized Actuated Valves

LOCATION: Binictican, SBMA Zambales
CLIENT: Subic Water and Sewerage Co. Inc
DURATION: April–May 2015

Ultrasonic Clamp-on Flowmeter Installation

Ultrasonic Clamp-on Flowmeter Installation

Ultrasonic Clamp-on Flowmeter Installation

Ultrasonic Clamp-on Flowmeter Installation

Ultrasonic Clamp-on Flowmeter Installation

LOCATION: Binictican, SBMA Zambales
CLIENT: Subic Water and Sewerage Co. Inc
DURATION:September 2017

PLC Installation (Filtration Plant)

PLC Installation (Filtration Plant)

PLC Installation (Filtration Plant)

PLC Installation (Filtration Plant)

PLC Installation (Filtration Plant)

LOCATION: Binictican, SBMA Zambales
CLIENT: Subic Water and Sewerage Co. Inc
DURATION: January 2018

AERO Digester Rehabilitation

AERO Digester Rehabilitation

AERO Digester Rehabilitation LOCATION:

AERO Digester Rehabilitation

AERO Digester Rehabilitation

LOCATION: Binictican, SBMA
Zambales
CLIENT: Subic Water and Sewerage Co. Inc.
DURATION: July — September 2018

Energy Development Corporation

Energy Development Corporation

Installation of New Counterflow

Energy Development Corporation

Installation of New Counterflow Cooling Tower

Energy Development Corporation

LOCATION: Ormoc, Leyte
PROJECT: Mahanagdong B- Rehabilitation of 8th Cell Counterflow Cooling Tower
DURATION: July –September 2017

Maibarara Geothermal Power Plant Phase II

Maibarara Geothermal Power Plant Phase II

Installation of New Counterflow

Maibarara Geothermal Power Plant Phase II

Installation of New Counterflow Cooling Tower

Maibarara Geothermal Power Plant Phase II

LOCATION: Sto. Tomas, Batangas
PROJECT: Maibarara Geothermal Power Plant Phase II
DURATION: July – August 2017

PRII Cooling Tower Turn-Around Project

PRII Cooling Tower Turn-Around Project

Cooling Tower Turn-Around Project

PRII Cooling Tower Turn-Around Project

Cooling Tower Turn-Around Project

PRII Cooling Tower Turn-Around Project

LOCATION: Mariveles, Bataan
PROJECT: PRII Cooling Tower Turn-Around Project
DURATION: November—December 2015

ANDA 82MW Coal Power Plant

ANDA 82MW Coal Power Plant

New Cooling Tower ANDA

ANDA 82MW Coal Power Plant

New Cooling Tower

ANDA 82MW Coal Power Plant

LOCATION: TIPCO Park, Mabalacat Pampanga
PROJECT: PETRON 2D Turn-Around Project
DURATION:  November 2014– January 2015

PETRON 2D Turn-Around Project

PETRON 2D Turn-Around Project

Cooling Tower PETRON 2D

PETRON 2D Turn-Around Project

Cooling Tower

PETRON 2D Turn-Around Project

LOCATION: Limay, Bataan
PROJECT: PETRON 2D Turn-Around Project
DURATION: January-February 2014

2 x 35MW Coal Power Plant (RSFFB-2)

new cooling tower

Petron Units 3&4 Project

LOCATION: Limay, Bataan
PROJECT: 2 x 35MW Coal Power Plant (RSFFB-2)
DURATION: July—October 2013