LOCATION: Brgy. Limao, Calauan, Laguna PROJECT: REPAIR OF VARIOUS COOLING TOWER STRUCTURE DUE TO TYPHOON PAENG
SCOPE OF WORK COMPLETED:
Replaced damaged louvers on various cooling tower units caused by Typhoon Paeng. The following details outline the number of louvers replaced per unit:
Unit 1: 66 pcs (East and West sides)
Unit 2: 22 pcs (East and West sides)
Unit 3: 3 pcs
Unit 4: 17 pcs (East and West sides)
Unit 5: 1 pc
Unit 9: 16 pcs (East and West sides); 10 pcs (both sides, estimated)
ABOITIZ POWER AND RENEWABLES INC. (MAKBAN GEOTHERMAL POWER PLANT)
MAKBAN GEOTHERMAL POWER PLANT
ABOITIZ POWER AND RENEWABLES INC.
LOCATION: Brgy. Limao, Calauan, Laguna PROJECT : REPAIR OF UNIT 8 COOLING TOWER STRUCTURE
SCOPE OF WORK COMPLETED:
Repaired the damaged distribution valve near CTF 8B cubicle (East side), including lapping of discs, leakage repair, and installation of discs and stem.
Repaired leakage on the distribution valve platform (CTF 8B), with lamination applied where necessary.
De-clogged and cleaned the clogged hot basin flower nozzles, and replaced missing nozzles (nozzles were supplied by APRI).
Tightened bolts on cooling tower structures.
Inspected and replaced missing splash bars (materials supplied by APRI).
Applied Vulcaseal sealant to the corners of hot basin flooring.
Inspected and replaced damaged transverse and longitudinal supports (2" x 6"), with FRP material provided by the end user.
Replaced/ repaired damaged louvers and sidings (manlift provided by the end user).
Inspected and installed missing drift eliminators on both the East and West sides of the cooling tower.
Replaced/ repaired dilapidated or damaged hot basin flooring with FRP materials (FRP materials were supplied by APRI).
ABOITIZ POWER AND RENEWABLES INC. (TIWI GEOTHERMAL POWER PLANT)
(TIWI GEOTHERMAL POWER PLANT)
ABOITIZ POWER AND RENEWABLES INC.
Project: UNIT 1 AND UNIT 2 COOLING TOWER STAIRCASE INSTALLATION
SCOPE OF WORK COMPLETED:
Installed cooling tower staircases for Units 1 and 2 at Tiwi Geothermal Power Plant, Barangay Naga, Tiwi, Albay, commissioned by Aboitiz Power and Renewables Inc.
Project completed in 20 days.
Mobilized and set up necessary facilities and safety measures.
Dismantled existing monkey ladders.
Installed new fiberglass-reinforced plastic (FRP) monkey ladders for Unit 1.
Completed foundation work: excavation, formwork, and concrete pouring for FRP staircases and bridge interconnections.
Installed tie backs and erected final staircase for Unit 2.
Dismantled old structures and hauled debris.
Conducted site walkthrough with the end user, testing, and commissioning.
Completed final tasks, including painting and de-mobilization.