(TIWI GEOTHERMAL POWER PLANT)
ABOITIZ POWER AND RENEWABLES INC.
Project: UNIT 1 AND UNIT 2 COOLING TOWER STAIRCASES INSTALLATION
SCOPE OF WORK COMPLETED:
- Installed cooling tower staircases for Units 1 and 2 at Tiwi Geothermal Power Plant, Barangay Naga, Tiwi, Albay, commissioned by Aboitiz Power and Renewables Inc.
- Project completed in 20 days.
- Mobilized and set up necessary facilities and safety measures.
- Dismantled existing monkey ladders.
- Installed new fiberglass-reinforced plastic (FRP) monkey ladders for Unit 1.
- Completed foundation work: excavation, formwork, and concrete pouring for FRP staircases and bridge interconnections.
- Installed tie backs and erected final staircase for Unit 2.
- Dismantled old structures and hauled debris.
- Conducted site walkthrough with the end user, testing, and commissioning.
- Completed final tasks, including painting and de-mobilization.