(TIWI GEOTHERMAL POWER PLANT)

ABOITIZ POWER AND RENEWABLES INC.

Project: UNIT 1 AND UNIT 2 COOLING TOWER STAIRCASES INSTALLATION


SCOPE OF WORK COMPLETED: 

  • Installed cooling tower staircases for Units 1 and 2 at Tiwi Geothermal Power Plant, Barangay Naga, Tiwi, Albay, commissioned by Aboitiz Power and Renewables Inc.
  • Project completed in 20 days.
  • Mobilized and set up necessary facilities and safety measures.
  • Dismantled existing monkey ladders.
  • Installed new fiberglass-reinforced plastic (FRP) monkey ladders for Unit 1.
  • Completed foundation work: excavation, formwork, and concrete pouring for FRP staircases and bridge interconnections.
  • Installed tie backs and erected final staircase for Unit 2.
  • Dismantled old structures and hauled debris.
  • Conducted site walkthrough with the end user, testing, and commissioning.
  • Completed final tasks, including painting and de-mobilization.